Development Plan: latest update
Posted: 4th July 2014
Phase One of our two year development plan is underway, with planned building work taking place over the Summer break.
Arts Block
Contractors have now been appointed for the new Arts Block.
Work will commence during July and be completed before the start of the new term.
All Weather playing surface
Contractors have now been appointed for the All Weather playing surface and a full planning application has been submitted.
Subject to the planning grant, we expect to commence work during August. The ground works will be completed around the beginning of September, with the carpet and fencing installed by early October.
IT framework
A new wireless network will be installed during the Summer break and discussions are in progress to improve the bandwidth connection into the school.